Process

From inquiry to your own power system - step by step

One point of contact handles the whole project. For every step you know who does it, how long it takes and what the outcome is. Overall: typically 3-6 months, with most of that time taken by the grid-connection procedure - not construction.

You IC Solar Grid operator (EPS)
  1. 1

    Inquiry and bill analysis

    You + IC Solar 1 day

    You send us your electricity bills for the last 12 months. From them we read your annual consumption profile - the basis for everything that follows.

    → A clear picture of your consumption and a first savings estimate

  2. 2

    Site visit

    IC Solar 1 day

    We visit the property: roof condition and load capacity, orientation, shading, cable routing, and the inverter and connection location.

    → Technical data for the design

  3. 3

    Savings simulation and quotation

    IC Solar 2-3 days

    We size the system to your consumption profile and simulate production. You receive a quotation with a configuration, price and payback calculation.

    → A concrete quotation with a savings simulation

  4. 4

    Contract

    You + IC Solar 1-2 days

    We define scope, timeline and payment schedule. You sign both the contract and a power of attorney authorizing us to represent you with the grid operator.

    → Signed contract - from here on, we manage everything

  5. 5

    Grid connection request and technical conditions

    IC Solar + EPS 4-8 weeks

    We submit the connection request and obtain the technical conditions. This is the longest part of the process, which is why we start it immediately after signing.

    → Approved connection conditions

  6. 6

    Design

    IC Solar 1-2 weeks

    Detailed design: panel layout, string configuration, structure, protection and connection - in line with the grid operator's technical conditions.

    → Design ready for construction

  7. 7

    Installation

    IC Solar 30 kW ≈ 5 days

    Our own crews install the structure, panels and inverter and connect the system. Your production doesn't stop - only a brief interruption during final connection, at a time you choose.

    → System physically ready

  8. 8

    Technical acceptance

    IC Solar + EPS 2-4 weeks

    Measurements, testing and acceptance by the grid operator. We prepare the complete documentation and attend the acceptance.

    → System approved to operate

  9. 9

    Commissioning and monitoring

    IC Solar 1 day

    We commission the system and set up monitoring - you can follow production from day one in the app, and so do we.

    → The system is producing; warranty and service support begin

Questions about the procedure and timelines

How long does the whole thing take - from inquiry to commissioning?

Typically 3 to 6 months. Installation itself is the shortest part (30 kW ≈ 5 working days); most of the time is spent on the grid-connection procedure - the connection request, technical conditions and technical acceptance. That is why we manage it and start it immediately after the contract is signed.

Does production stop at your site during installation?

No. Roof work does not touch your process; a brief power interruption is only needed when connecting to your installation, and we schedule it at a time that works for you.

What do you need from us during the procedure?

At minimum: 12 months of bills at the start, site access for the visit, and your signature on the contract and the power of attorney to represent you with the grid operator. Everything else - measurements, design, applications, filings - is our job.

Who signs the contract with the grid operator?

You sign the full-supply contract as the customer-producer, but we prepare and manage the entire procedure up to signing - you receive a ready document.

Your part of the work

Three signatures and your bills - we handle the rest

From you we need 12 months of bills, access to the site, and signatures on the contract and power of attorney. Every application, design and acceptance is on us.

Start the first step

Calculate the savings for your property

Send us your electricity bills for the last 12 months and your site location - you will get a quotation with a savings simulation in 2-3 days.